School District of Clay County
Green Cove Springs, Florida
Teacher Inservice Center - Fleming Island High School 2233 Village Square Parkway Hearings for Special Actions regarding Students - 4:00 p.m. REGULAR MEETING - 7:00 p.m.
September 17, 2007 Regular Meeting
Agenda Item #32


Item Title
C-31 Change Order #2 for Chiller Replacement at Lake Asbury Elementary School

Issue/Rationale

Change Orders are initiated by the Contractor, Architect/Engineer or Owner, which may increase or decrease the scope of the project as defined by the plans and specifications. Once a change order is initiated, review/evaluation is undertaken to determine the merit and/or requirements of the change order. Change orders affect the scope of the project and are required to be School Board approved by State Requirements for Educational Facilities and Florida Statutes. See Attachment for details.

 



Recommended Action

Approve Change Order #2 as submitted.



Financial Impact
$13,071.00. This addition to the construction contract will be paid from Special Maintenance Section III funds.

Submitted By
Thomas L. Smith, Director of Maintenance & Operations


Attachment:  CO2.LAE.Chiller 002.pdf